Power system maintenancePlanned Maintenance

Description

The data center has scheduled preventive maintenance of the diesel rotary uninterruptible power supply (DRUPS) in the listed location. The power feed redundancy status will stay the same during the maintenance, but the battery protection will be temporarily reduced. The works will be carried out in four stages: Stage 1: January 13, 2026 06:00 (UTC) - January 13, 2026 16:00 (UTC) January 13, 2026 09:00 (MSK) - January 13, 2026 19:00 (MSK) Stage 2: January 16, 2026 20:00 (UTC) - January 17, 2026 05:00 (UTC) January 16, 2026 23:00 (MSK) - January 17, 2026 08:00 (MSK) Stage 3: January 23, 2026 20:00 (UTC) - January 24, 2026 05:00 (UTC) January 23, 2026 23:00 (MSK) - January 24, 2026 08:00 (MSK) Stage 4: January 30, 2026 20:00 (UTC) - January 31, 2026 05:00 (UTC) January 30, 2026 23:00 (MSK) - January 31, 2026 08:00 (MSK) Unavailability of your servers is not expected.

Components

Power system

Locations

MOW1

Schedule

January 13, 2026 09:00 - January 31, 2026 08:00 MSK
January 13, 2026 06:00 - January 31, 2026 05:00 UTC



January 13, 2026 14:43 MSK
January 13, 2026 11:43 UTC
UPDATE

Stage 1 of the scheduled maintenance has been completed successfully. Related services are operating normally.

January 13, 2026 09:00 MSK
January 13, 2026 06:00 UTC
UPDATE

Stage 1 of the scheduled maintenance has begun.

Servers.ru Website




Operational


Portal - portal.servers.ru




Operational


Ticket/e-mail system




Operational


Public Network




Operational


Global Private Network




Operational


Direct Connect




Operational


Power system




Planned Maintenance


Cloud Servers




Operational


Cloud Storage




Operational


Load Balancers




Operational


Firewall




Operational


Kubernetes




Operational


Public API




Operational


VPN to DRAC




Operational


VPN to Global Private Network




Operational


DNS resolver




Operational


Authoritative DNS




Operational


Scheduled Maintenance

Power system maintenancePlanned Maintenance

Schedule

January 21, 2026 09:00 - January 22, 2026 17:00 MSK
January 21, 2026 06:00 - January 22, 2026 14:00 UTC

Components

Power system

Locations

MOW3

Description

The data center has scheduled preventive maintenance of the diesel generator sets (DGS) in the listed location. During the maintenance, the racks will be powered from the utility power grid and supported by uninterruptible power supply (UPS). The works will be carried out in two stages: Stage 1: January 21, 2026, 06:00 - 10:00 (UTC) January 21, 2026, 09:00 - 13:00 (MSK) Stage 2: January 22, 2026, 06:00 - 14:00 (UTC) January 22, 2026, 09:00 - 17:00 (MSK) Unavailability of your servers is not expected.